QubitPage Technical Dossier

SENTINEL Production Guide

Full production blueprint — facility layout, 5M capital budget, equipment list, 21-person team structure, monthly operating costs, R&D timeline, GPU datacenter, and break-even analysis.

LocationCiurila, Cluj
Total Area2,400 m²
Production Hall1,200 m²
Solar200 kWp

1 — Site & Facility

All SENTINEL models are manufactured at a purpose-built facility in Comuna Ciurila, Cluj County, Romania. The location offers EU single-market access, elite STEM talent from Cluj-Napoca technical universities, and operating costs 2–3x lower than Western Europe.

Total footprint: 2,400 m² with a 1,200 m² production hall, ISO 7 cleanroom for electronics assembly, a dedicated testing lab, warehouse/logistics zone, office block, and rooftop solar array (200 kWp) with grid backup targeting net-zero production by Year 2.

2 — Capital Budget (€5M)

CategoryAmount% of Total
Facility Build-out€1,200,00024%
Production Equipment€1,800,00036%
Initial Inventory€500,00010%
Working Capital€1,500,00030%

3 — Production Equipment

  • CNC 5-axis machining centre — aluminium frame fabrication
  • Laser cutter — sheet metal and composite panels
  • 3D metal printer (SLM) — custom brackets and SENTINEL-LINK housings
  • SMT pick-and-place line — PCB assembly
  • Environmental test chamber — IP67/IP68 and MIL-STD validation
  • 6-axis robot welding cell — frame joining
  • Coordinate Measuring Machine (CMM) — quality control
  • Battery pack assembly station with spot welding

4 — Personnel (21 staff)

RoleCountGross/Month
Production Manager1€4,200
Senior Mechanical Engineer2€3,800
Embedded Systems Engineer2€4,200
AI/ML Engineer2€4,500
Assembly Technician6€1,800
Quality Inspector2€2,200
Warehouse/Logistics2€1,600
R&D Intern / Junior2€1,200
Admin / HR / Finance2€2,000

Monthly payroll: ~€55,800 (including employer social contributions at +26%).

5 — Monthly Operating Costs

ItemMonthly
Payroll (21 staff)€55,800
Utilities & Maintenance€4,500
Insurance€2,800
IT & Software Licences€3,200
Miscellaneous€2,500

6 — R&D Timeline

  • Months 0–6: Facility construction, equipment procurement, SENTINEL-WH prototype refinement.
  • Months 6–12: Production line commissioning. First 50 SENTINEL-WH units to pilot customers.
  • Months 12–18: SENTINEL-AG line brought online. Start SENTINEL-HM prototyping.
  • Months 18–24: 150 units/year steady-state. SENTINEL-MK certification begins.
  • Months 24–36: SENTINEL-MK delivery. GPU datacenter expansion. 450+ units/year.

7 — GPU Datacenter

An on-site GPU datacenter equipped with NVIDIA DGX A100 systems handles AI model training, inference benchmarking, and fleet OTA update staging. The datacenter is also offered as a service to investors via QubitPage Foundation credits.

8 — Break-Even Analysis

At 150 units/year (SENTINEL-WH at €42,000), annual revenue reaches €6.3M against ~€3.2M in COGS and ~€0.8M in operating expenses, yielding positive EBITDA by Month 18. Full €5M investment ROI projected within 36 months.